KOLLAM

SECTOR WISE

SECTORTOTAL PROJECTSPROJECT COSTAS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITUREEXPENDITURE %
WS17103.8417121.1917121.1917121.1917103.421239.3632.48
SEW387.743125.52229.87229.87231.91000.00
SWD2132.202129.172129.912129.912129.731318.8764.68
UT1124.441122.381019.231019.2388.8163.9117.45
GSP75.2373.7373.3173.3173.2573.0381.28
TOTAL59253.4559301.9957203.5157203.5155177.123865.1721.58
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORMWATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

AGENCY WISE [KWA]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS1517115.8515115.8517115.851598.081239.3633.97
SEW33125.52229.87229.87231.91000
TOTAL1818241.3717145.7217145.7217129.991239.3616.31

AGENCY WISE [ULB]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS225.3425.3425.3425.34000
SEW000.0000.0000.0000.00000
SWD212129.172129.912129.912129.731318.8764.68
UP111122.381019.231019.2388.8163.9117.45
GSP773.7373.3173.3173.2573.0381.28
TOTAL414160.634057.794057.793847.132625.8142.57

Last Updated on 18/10/2021