SEPTAGE TREATMENT PLANT [AS ON 30.11.2020]

ABSTRACT

CATEGORYNUMBER OF PLANTSCOST (IN CRORE)CITY
Work started27.92Guruvayur- 1, Kannur-1
Awarded but Agreement not executed311.13Thrissur- 1, Palakkad- 1, Kollam- 1
TS to be issued20.80Alappuzha- 2
Cancelled28.44Kollam- 2
TOTAL928.29z

IMPLEMENTED BY ULB

PLANT NUMBERWORK NUMBERCITYCONSULTANTPROJECT DETAILSSTATUS
11KollamRam Biologicals100 KLD Septage Treatment Plant at Andamukkam
(Electro Coagulation)
AS: Rs.12.66Cr., Dt: 22.02.2018
TS: Rs.9.8Cr., Dt: 22.08.2018
Combined AS & TS for No.1, 2 & 3
Awarded but agreement not executed
22KollamRam Biologicals100 KLD Septage Treatment Plant Vasoorichira
(Electro Coagulation)
Combined AS & TS for No.1, 2 & 3
Cancelled
33KollamRam Biologicals100 KLD Septage Treatment Plant Karikkuzhi Ela
(Electro Coagulation)
Combined AS & TS for No.1, 2 & 3
Cancelled
4 & 54AlappuzhaRam Biologicals10 KLD mobile Septage unit – 2 Numbers.
(Electro Coagulation)
AS: Rs.0.8Cr., Dt: 30.03.2019
TS to be issued
65ThrissurRam BiologicalsSeptage Treatment Plant of 100 KLD at Ramavarmapuram
(Electro Coagulation)
AS: Rs.3.5Cr., Dt: 01.01.2018
TS: Rs.3.1Cr., Dt: 28.06.2018
Awarded but agreement not executed
76GuruvayurRam Biologicals100 KLD Septage Plant at Chakkumkandam
(Electro Coagulation)
AS: Rs.4.5Cr., Dt: 31.05.2018
TS: Rs.3.9Cr., Dt: 30.07.2018
Work started
87PalakkadRam Biologicals100 KLD Septage Treatment Plant at Yakkara
(Electro Coagulation)
AS: Rs.3.41Cr., Dt: 23.12.2017
TS: Rs.3Cr., Dt: 30.06.2018
Awarded but agreement not executed
98KannurRam Biologicals100 KLD Septage Treatment Plant at Chellora
(Electro Coagulation)
AS: Rs.3.42Cr., Dt: 23.12.2017
TS : Rs. 3.1Cr. Dt.28.06.2018
Work started