SEPTAGE TREATMENT PLANT – IMPLEMENTED BY ULB

ABSTRACT

CATEGORYNUMBER OF PLANTSCOST (IN CRORE)CITY
WORK STARTED14.50Guruvayur- 1
Agreement executed but not started13.42Kannur-1
Awarded but Agreement not executed13.5Thrissur- 1
Tendered but not awarded27.63Palakkad- 1, Kollam- 1
To be re-tendered14.22Kollam- 1
TS not issued20.80Alappuzha- 2
To be cancelled11.22Kollam- 1
TOTAL928.29

DETAILS

PLANT NUMBERWORK NUMBERCITYCONSULTANTPROJECT DETAILS
11KollamRam Biologicals100 KLD Septage Treatment Plant at Andamukkam
(Electro Coagulation)
AS: Rs.12.66Cr., Dt: 22.02.2018
TS: Rs.9.8Cr., Dt: 22.08.2018
Combined AS & TS for No.7, 8 & 9
22KollamRam Biologicals100 KLD Septage Treatment Plant Vasoorichira
(Electro Coagulation)
Combined AS & TS for No.7, 8 & 9
33KollamRam Biologicals100 KLD Septage Treatment Plant Karikkuzhi Ela
(Electro Coagulation)
Combined AS & TS for No.7, 8 & 9
4 & 54AlappuzhaRam Biologicals10 KLD mobile Septage unit 2 nos.
(Electro Coagulation)
AS: Rs.0.8Cr., Dt: 30.03.2019
65ThrissurRam BiologicalsSeptage Treatment Plant of 100 KLD
(Electro Coagulation)
AS: Rs.3.5Cr., Dt: 01.01.2018
TS: Rs.3.1Cr., Dt: 28.06.2018
76GuruvayurRam Biologicals100 KLD Septage Plant at Chakkumkandam
(Electro Coagulation)
AS: Rs.4.5Cr., Dt: 31.05.2018
TS: Rs.3.9Cr., Dt: 30.07.2018
87PalakkadRam Biologicals100 KLD Septage Treatment Plant at Yakkara
(Electro Coagulation)
AS: Rs.3.41Cr., Dt: 23.12.2017
TS: Rs.3Cr., Dt: 30.06.2018
98KannurRam Biologicals100 KLD Septage Treatment Plant at Chellora
(Electro Coagulation)
AS: Rs.3.42Cr., Dt: 23.12.2017
TS : Rs. 3.1Cr. Dt.28.06.2018