SEPTAGE TREATMENT PLANT [AS ON 11.10.2021]

ABSTRACT

CATEGORYNUMBER OF PLANTSCOST (IN CRORE)CITY
Work started but stalled27.92Kannur-1, Guruvayur-1
Selection notice issued but agreement to be executed26.50Thrissur- 1, Palakkad- 1
To be tendered20.80Alappuzha- 2
TOTAL615.22

IMPLEMENTED BY ULB

PLANT NUMBERWORK NUMBERCITYPROJECT DETAILSEXPECTED DATE OF COMPLETIONSTATUS

1

1

Kannur
100 KLD Septage Treatment Plant at Chellora
(Electro Coagulation)
AS: Rs.3.42Cr., Dt: 23.12.2017
TS: Rs. 3.1Cr. Dt. 28.06.2018

31.03.2022

Work started but stalled

2

2

Guruvayur
100 KLD Septage Plant at Chakkumkandam
(Electro Coagulation)
AS: Rs.4.5Cr., Dt: 31.05.2018
TS: Rs.3.9Cr., Dt: 30.07.2018

31.03.2022

Work started but stalled

3

3

Thrissur
Septage Treatment Plant of 100 KLD at Ramavarmapuram
(Electro Coagulation)
AS: Rs.3.5Cr., Dt: 01.01.2018
TS: Rs.3.1Cr., Dt: 28.06.2018

31.03.2022

Selection notice issued but agreement to be executed

4

4

Palakkad
100 KLD Septage Treatment Plant at Yakkara
(Electro Coagulation)
AS: Rs.3 Cr. (Revalidated to 3 Cr. from 3.41 Cr. Dt. 10.03.2021)
TS: Rs.3Cr., Dt: 30.06.2018

31.03.2022

Selection notice issued but agreement to be executed
5&65Alappuzha10 KLD mobile Septage unit –
2 Numbers.
(Electro Coagulation)
AS: Rs.0.8Cr., Dt: 30.03.2019
31.03.2022To be tendered