SEWAGE TREATMENT PLANT

ABSTRACT

CATEGORYNUMBER OF PLANTSCOST (IN CRORE)CAPACITY IN MLDCITY
Work completed235.6810Thiruvananthapuram Med. College- 1(5 MLD)
Kochi- Elamkulam – 1 (5 MLD)
Work in progress695.5316.6Kollam-1 (Kureepuzha 12 MLD) ,
Alappuzha-1(General hospital 0.24 MLD),
Kozhikode- 2(Med. College 2 MLD & 1MLD) ,
Kannur- 1( Padannapalam 1 MLD),
Thrissur-1( General Hospital 0.36 MLD)
Awarded but not started115.501.1Kochi- 1 (Division 16 – 1.1 MLD)
Tendered but not awarded12.240.05Alappuzha- 1 (Thottumadi Colony- 50 KLD )
TOTAL10148.9527.75

IMPLEMENTED BY ULB

PLANT NUMBERWork NumberAgency
City

Project Details
Expected Date of Completion
Status
REMARKS


1


1&2


KWA


Thiruvananthapuram
5 MLD Sewage Treatment Plant
at Medical College, Trivandrum
Phase I & II
(Biological-MBBR)
AS: Rs.19.16Cr., Dt: 23.02.2017
TS: Rs.19.16Cr., Dt: 25.09.2018


Work completed & commissioned


Work Completed


Nil
23KWAKochiRejuvenation of 5 MLD Sewage Treatment Plant at Elamkulam
(Biological-MBBR)
AS: Rs.16.52Cr., Dt: 25.01.2020
TS: Rs.13.70Cr., Dt: 15.02.2018
The lab work is to be completed by 31.07.2023Work CompletedNIL


3


4&5


KWA


Kollam
12 MLD Sewage Treatment Plant
at Kureepuzha- Phase I & II
(Biological-MBBR)
AS: Rs.31.92Cr., Dt: 17.06.2020
TS: Rs.29.86Cr., Dt: 28.09.2021


31.07.2023


Work in progress (Physical progress 82%)


Land to be acquired (27 cents) for FSTP component


4


6


ULB


Kannur
Providing Decentralized Sewerage Network
with Sewage Treatment Plant in old Kannur Municipal area
(1 MLD* Plant at Padanna Palam)
(Biological-RMBR)
AS: Rs.41.54 Cr., Dt: 01.01.2018
TS: Rs.23.6Cr., Dt: 02.03.2019


31.07.2023



Work in progress (Physical progress 95%)


Nil


5


7&8


ULB


Alappuzha
Construction of Sewage Treatment Plant
at General Hospital, Alappuzha.
(240 KLD* – Phase I & II)
(Electro Coagulation)
AS: Rs.3.45Cr., Dt: 01.01.2018
TS: Rs.3.05Cr., Dt: 30.07.2018


31.07.2023


Work in progress (Physical progress 75%)


Nil


6&7


9


ULB


Kozhikode
Sewage Treatment Plant with Septage Treatment
(1 MLD* & 2.1 MLD* Plants) at Medical College, Kozhikode
(Electro Coagulation)
AS: Rs.14.12Cr., Dt: 13.11.2017
TS: Rs.14.11Cr., Dt: 30.07.2018


15.08.2023


Work in progress (Physical progress 70%)


Nil
810ULBThrissurSewerage Treatment Plant of 360 KLD* capacity
at General Hospital, Thrissur
(Electro Coagulation)
AS: Rs.4.50Cr., Dt: 27.12.2022
TS: Rs.3.52Cr., Dt: 30.07.2018
31.12.2023Work in progress (Physical progress 50%)Nil


9


11


ULB


Kochi
Implementation of a Decentralized Sewerage system
for Division-16 ( Edakochi South – STP at Ambedkar Colony)
(Biological-SBR)
Div-16: 1.1 MLD* Plant
AS: Rs.44.56Cr. Dt: 23.12.2017)
Combined AS for No.10, 15 & 16
TS: Rs.15.50Cr., Dt: 11.09.2018
(Rs.18.66 Cr. including tender excess)


30.06.2024


Awarded but not started


Public Protest


10


12


ULB


Alappuzha
50 KLD Sewage Treatment Plant with the associated network
at Thottumadi Colony
(Biological-RMBR)
AS: Rs.2.24Cr., Dt: 16.12.2019
TS: Rs.2.24 Cr., Dt: 13.08.2021


31.03.2024


Tendered but not awarded


Procedural delay
*MLD – Million Litre per Day, KLD- Kilo Litre per Day (Denote Capacity)