100 DAYS PROGRAM - Phase 3 (from 10th February 2023 to 20th May 2023)
Target: Completion & Inauguration of 8 Projects worth Rs.114.64 Cr.
- In-Progress (1 Work | 31.92 Cr.)
- Completed (7 Works | 82.72 Cr.)
S. No. | City | Project Name | Project Cost | Physical Status |
1 | Kollam | 12 MLD Sewage treatment plant at Kureeppuzha(Phase1 &2) | 31.92 | 80% |
S. No. | City | Project Name | Project Cost | Physical Status |
1 | Guruvayur | Development of parks and playground at Bhagath Singh ground | 1 | Completed & Inaugurated |
2 | Alappuzha | Improvement of vadapozhi | 2.4 | Completed & Inaugurated |
3 | Kochi | Construction of 25LL OHSR at Karuvelippady | 11.65 | Completed & Inaugurated |
4 | Kochi | Construction of 17LL OHSR and CWR at Pachalam | 7.75 | Completed |
5 | Kochi | 5 MLD Sewerage Treatment Plant with FSTP Co-treatment at Elamkulam, Kochi | 16.52 | Completed & Ready for the inauguration |
6 | Kannur | 1 MLD STP & Network at Padannappalam, Kannur | 41.54 | Completed |
7 | Kannur | Development of a new park at Chelora near the trenching ground | 1.86 | Completed |
Total | 82.72 Cr. |
- Completed (24 Works | 237.09 Cr.)
- In-Progress (4 Works | 17.25 Cr.)
S. No. | City | Project Name | Project Cost in Cr. | Physical Status |
1 | Thiruvananthapuram | Construction of Smart Office in Thiruvananthapuram- Kowdiar | 1.75 | Completed |
2 | Thriuvananthapuram | Providing sewerage facility to Eastern side of Amayizhanjanthodu between Vanchiyoor Jn & Samad Hospital road jn. | 0.215 | Completed |
3 | Thriuvananthapuram | TSS – Urgent laying of 300mm dia HDPE pipe & construction of new manholes at Chengalloor & Vattavila of Punnakkamugal ward. | 1.03 | Completed |
4 | Alappuzha | Improvement of Thumboly pozhi | 3.5 | Completed |
5 | Alappuzha | Construction of 28.00LL Capacity OHSR at Valiyakulam(Zone-VII) | 12.19 | Completed |
6 | Kochi | Renovation of Karanakodam Thodu & Adimurithodu | 2.83 | Completed |
7 | Thrissur | AMRUT-2015-16 Completion of ongoing Schemes –UWSS TO Ollur&Edakkunni Census Town Villages in Thrissur Corporation –Construction of 20LL Capacity OHSR at Ollur& Supplying, Laying Distribution lines and construction of retaining wall at WTP,Arattupuzha. | 13.96 | Completed |
8 | Thrissur | Strengthening the existing distribution system to Thrissur Corporation area – Replacement of very old 80/100/125/300 mm AC &700mm premo pipes with 110/140 mm PVC and 200/300/350 mm D1 pipes at various places in Thrissur Corporation-Phase-1 | 14.4 | Completed |
9 | Thrissur | Laying of distribution lines from existing OHT at Kizhakumpattukara to Nellikunnu area for around 15 km with varing dia pipelines-(Dia 200 mm DI to 110 mm PVC) | 6 | Completed |
10 | Palakkad | AMRUT Phase II – Construction of 45 MLD water treatment plant at Malampuzha, KWA compound and booster station. | 22.15 | Completed |
11 | Palakkad | AMRUT Phase III – Providing Rider main pipelines, Replacing AC pipelines and service connection for proper zoning | 28.11 | Completed |
(Part-I) : Mattumantha Zone- 46.933km (600mm DI K9 -200mm DI K9 &160mm PVC) | ||||
12 | Palakkad | (Part-II) : Moothanthara Zone-47.613km (600mm DI K9 -200mm DI K9 &160mm PVC) | 29.21 | Completed |
13 | Palakkad | (Part-II) : Kalmandapam Zone-47.613km (600mm DI K9 -200mm DI K9 &160mm PVC) | 27.83 | Completed |
14 | Palakkad | Nila Nagar Park | 0.37 | Completed |
15 | Palakkad | FOB at Govt Moyan’s High School | 0.55 | Completed |
16 | Kozhikode | Strengthening of existing infrastructure facilities, and quality improvement of CWSSin Kozhikode corporation,Package I | 8.7 | Completed |
17 | Kannur | Mullankandi thodu & connecting drains | 3.38 | Completed |
18 | Kannur | Anjukandy & connecting drains | 2.62 | Completed |
19 | Guruvayur | Construction of Multilevel Car Parking – Phase I & II | 21.85 | Inaugurated |
20 | Guruvayur | SAAP 2015-16, 2016-17, 2017-18 Package I – Covering and repair of minor drains in 16 different locations of the municipal area- PACKAGE IA-drains with footpath | 7.82 | Inaugurated |
21 | Guruvayur | SAAP 2015-16, 2016-17, 2017-18 Package I – Covering and repair of minor drains in 16 different locations of the municipal area-PACKAGE IB-drains without footpath | 4.81 | Inaugurated |
22 | Guruvayur | Construction of footpaths in 4 locations in Temple Circle Areas | 8.57 | Inaugurated |
23 | Palakkad | Venkiteshwara Garden Park | 0.25 | Completed |
24 | Kochi | Construction of 40LL capacity OHSR at Kaloor | 15 | Completed |
Total | 237.09 |
S. No. | City | Project Name | Project Cost in Cr. | Physical Status |
1 | Thiruvananthapuram | Supply and Installation of smart meters (Phase I) | 1.27 | 86% Completed |
2 | Kochi | Construction of 40LL capacity OHSR at Kaloor | 15.00 | 99%Completed |
3 | Palakkad | Paved footpath along Stadium – Byepass – IMA Road | 0.73 | 92% Completed |
Total | 17.00 |
100 DAYS PROGRAM - PHASE 1
TARGET
Completion & Inauguration of 34 Works
worth Rs. 216.91 Crore
COMPLETED (100%)
28 Projects worth Rs. 99.59 Crore
IN PROGRESS (95.5%)
6 Projects worth Rs. 117.32 Crore
- In Progress (6 Works, 117.32 Cr.)
- Completed (28 Works, 99.59 Cr.)
Sl. No. | City | Name of Work | Project Cost (Rs. Cr.) | Current Status |
1 | Palakkad | Augmentation of Water Supply Scheme to Palakkad Muncipality: Mattumantha Zone- 46.933km (600mm DI K9 -200mm DI K9 &160mm PVC) | 85.15 | 97% Completed |
2 | Palakkad | Augmentation of Water Supply Scheme to Palakkad Muncipality: Moothanthara Zone-47.613km (600mm DI K9 -200mm DI K9 &160mm PVC) | 97% Completed | |
3 | Palakkad | Augmentation of Water Supply Scheme to Palakkad Muncipality: Kalmandapam Zone-43.996km (450mm DI K9 -200mm DI K9 &160mm PVC) | 98% Completed | |
4 | Thrissur | Strengthening the existing distribution system to Thrissur corporation area – Replacement of very old 80/100/125/300 mm AC &700mm premo pipes with 110/140 mm PVC and 200/300/350 mm D1 pipes at various places in Thrissur Corporation-Phase-2 | 12.95 | 96% Completed |
5 | Thrissur | AMRUT-2015-16 Completion of ongoing Schemes –UWSS TO Ollur&Edakkunni Census Town Villages in Thrissur Corporation –Construction of 20LL Capacity OHSR at Ollur& Supplying, Laying Distribution lines and construction of retaining wall at WTP,Arattupuzha. | 11.40 | 97% Completed |
6 | Guruvayur | SAAP 2015-16, 2016-17, 2017-18 Package I – Covering and repair of minor drains in 16 different locations of the municipal area – PACKAGE IA – drains with footpath | 7.82 | 92% Completed |
Total | 117.32 |
Sl. No. | City | Name of Work | Project Cost (Rs. Cr.) | Current Status |
1 | Thiruvananthapuram | Improvements of Water Supply Scheme- Construction of 75MLD Water Treatment Plant at Aruvikkara | 56.29 | Completed |
2 | Thrissur | AMRUT – Zoning and mapping of water supply system of Thrissur Corporation – Supply and laying of various dia pipes – Part I | 8.00 | Completed |
3 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 2 (Div 31, OLLUR CHURCH-CONVENT ROAD, CONVENT ROAD, PALLINADA ROAD PART 1, PALLINADA ROAD PART 2) Work 54 | 1.42 | Completed |
4 | Thrissur | AMRUT URBAN TRANSPORT UR MUNICIPAL CORPORATION Phase 2 (Div 3, Aswani Junction – Pattraikal – Girija Theatre – Viyyur bridge) Work 58 | 0.98 | Completed |
5 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 2 (Div 20, Jesus Lane Road, Alukka Angadi Road, Nazerth Angadi Road) Work 44 | 0.97 | Completed |
6 | Thrissur | Rejuvenation of Nehru Park, Division No.36,Thekkinkadu-phase-3 | 0.93 | Completed |
7 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION, PHASE 1 (Div 35. Mundupalam Junction -Avenue Rd-Aristo Rd Part 1,Mundupalam Junction -Avenue Rd-Aristo Rd Part 2) WORK 18 | 0.85 | Completed |
8 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 2 (Div 20, Paravattani Nellikkunnu Jn) Work 43 | 0.74 | Completed |
9 | Thrissur | AMRUT SWD AND URBAN TRANSPORT PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 2 (Div 9,Cheroor school-Cherutta Road) Work 41 | 0.57 | Completed |
10 | Thrissur | AMRUT URBAN TRANSPORT PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 2 (Div 35, Aristo road-St. Joseph convent girls School) Work 56 | 0.41 | Completed |
11 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 3 (Div 32,CHIYYARAM SOUTH-PALAKKAL MAIN ROAD) Work 80 | 0.28 | Completed |
12 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION, PHASE 1(, Div 35. WEST SIDE OF SAKTHAN BUS STAND) WORK 17 | 0.25 | Completed |
13 | Thrissur | AMRUT SWD PROJECT FOR THRISSUR MUNICIPAL CORPORATION Phase 2 (Div ,Peringavu -Cheroor Road) Work 39 | 0.22 | Completed |
14 | Palakkad | Kalvakkulam Thodu desilting and side wall- from stadium stand to Ramanadapuram | 1.54 | Completed |
15 | Palakkad | Manalai- Ramanadhapuram- Aanachira drain | 1.00 | Completed |
16 | Palakkad | Head Post office to Ramanadhapuram via Koppam drain | 0.98 | Completed |
17 | Palakkad | Manakkatodi secondary drain | 0.5 | Completed |
18 | Palakkad | Vandana layout park | 0.2 | Completed |
19 | Kozhikode | Integrated calicut WSP- Phase 2 Laying distribution line in 10 zones (SAAP 17-18)- Pottammal | 6.80 | Completed |
20 | Kozhikode | Strengthening of existing infrastructure facilities, and quality improvement of CWSS (SAAP 16-17) Phase 3 Package 2 Civil | 2.70 | Completed |
21 | Kozhikode | Integrated calicut WSP- Phase 2 Laying distribution line in 10 zones (SAAP 17-18)- Eravathkunnu north | 1.92 | Completed |
22 | Kozhikode | Rehabilitation of old valves, interconnections with existing lines and providing water meters in Kozhikode Corporation – Phase I (SAAP 15-16) Package VII | 0.68 | Completed |
23 | Kozhikode | Renovation of Garudankulam park | 0.51 | Completed |
24 | Kochi | Augmentation of Kochi WSS, Improvements of water supply to western Kochi area- Construction of 15L GL Tank at Karuvelipady | 3.20 | Completed |
25 | Kochi | Walkway along Kadavanthara to KV school&Market | 1.27 | Completed |
26 | Kochi | Kudumbi Colony Green Space | 0.71 | Completed |
27 | Kannur | Construction of cycle track phase II | 0.39 | Completed |
28 | Alappuzha | Construction of 21 LL OHSR at Kommadi(Zone-1) | 5.28 | Completed |
Total | 99.59 |