THRISSUR

SECTORTOTAL PROJECTSPROJECT COST*AS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITUREEXPENDITURE %
WS20139.1020136.1719130.0219130.0219130.02480.5959.18
SEW361.00360.42352.92352.9226.6200.000.00
SWD6145.966141.316137.576137.576137.574923.4156.67
UT2018.982017.082013.042013.042013.0483.2719.17
GSP64.8964.8964.6864.6864.6821.8537.83
TOTAL110269.93110259.87109238.23109238.23108191.9363109.1241.99
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORMWATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

Last Updated on 01/12/2020 by amrutker_smart