THIRUVANANTHAPURAM

SECTOR WISE

SECTORTOTAL PROJECTSPROJECT COST*AS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITURE*EXPENDITURE %
WS4599.044599.044597.454597.454587.594179.3280.09
SEW114159.81114176.24114153.25114153.25110160.218478.4444.51
SWD10361.0710347.2610345.9610345.9610339.6410033.6871.26
UT431.73431.73428.73428.73429.9915.6617.84
GSP45.8545.8545.8545.8545.7813.4559.05
TOTAL270357.50270360.12270331.24270331.24266323.21227200.5555.69
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORM WATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

AGENCY WISE [KWA]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS454599.044597.454597.454587.594179.3280.09
SEW114114176.24114153.25114153.25110160.218478.4444.51
KWA TOTAL159159275.28159250.70159250.70155247.80125157.7657.31

AGENCY WISE [ULB]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
SWD10310347.2610345.9610345.9610339.6410033.6871.26
UT4431.73428.73428.73429.9915.6617.84
GSP445.8545.8545.8545.7813.4559.05
TOTAL11111184.8411180.5411180.5411175.4110242.7950.44

Last Updated on 18/10/2021