PALAKKAD

SECTOR WISE

SECTORTOTAL PROJECTSPROJECT COST*AS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITUREEXPENDITURE %
WS11109.3311127.9511109.3311109.331192.74475.7359.19
SEW332.34315.08315.08313.34211.4800.000.00
SWD8338.958334.508338.138338.138334.137025.1372.83
UT3232.933233.753230.833228.933229.781516.3248.35
GSP218.20218.74218.74218.59216.53124.0746.55
TOTAL150221.75150220.02150202.11150198.32149174.66101121.2555.11
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORMWATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

AGENCY WISE [KWA]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS1111127.9511109.3311109.331192.74475.7459.19
TOTAL1111127.9511109.3311109.331192.74475.7459.19

AGENCY WISE [ULB]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
SEW3315.08315.08313.34211.48000
SWD838334.508338.138338.138334.137025.1372.83
UT323233.753230.833228.933229.791516.3248.35
GSP21218.74218.74218.59216.53124.0746.55
TOTAL13913992.0713992.7813988.9913881.929745.5149.43

Last Updated on 03/08/2021