KANNUR

SECTOR WISE

SECTORTOTAL PROJECTSPROJECT COST*AS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITUREEXPENDITURE %
WS12114.5212117.3912117.3912117.3912117.3912117.39100.00
SEW250.23250.23226.70226.70225.4200.000.00
SWD1239.601236.681236.681236.561236.31414.8840.57
UT516.75516.75513.82513.82513.5432.2713.55
GSP74.6274.6074.5574.5574.5552.3751.52
TOTAL38225.7238225.6538199.1438199.0238197.2124136.9160.67
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORMWATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

AGENCY WISE [KWA]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS1212117.3912117.3912117.3912117.3912117.39100.00
TOTAL1212117.3912117.3912117.3912117.3912117.39100.00

AGENCY WISE [ULB]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
SEW2250.23226.70226.70225.42000
SWD121236.681236.681236.561236.31414.8840.57
UT5516.75513.82513.82513.5432.2713.55
GSP774.6074.5574.5574.5552.3751.52
TOTAL2626108.262681.752681.632679.821219.5218.03

Last Updated on 03/08/2021