KANNUR

SECTOR WISE

SECTORTOTAL PROJECTSPROJECT COST*AS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITUREEXPENDITURE %
WS12114.5212117.3912117.3912117.3912117.3912113.1396.37
SEW250.23250.23226.70226.70225.4200.000.00
SWD1239.601239.601237.751237.751236.31413.3133.61
UT516.75513.83513.82513.82513.5431.5911.49
GSP74.6274.6074.5574.5574.5551.9742.82
TOTAL38225.7238225.6538200.2138200.2138197.2124130.0057.61
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORMWATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

AGENCY WISE [KWA]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS1212117.3912117.3912117.3912117.3912113.1396.37
TOTAL1212117.3912117.3912117.3912117.3912113.1396.37

AGENCY WISE [ULB]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
SEW2250.23226.70226.70225.42000
SWD121239.601237.751237.751236.31413.3133.61
UT5513.83513.82513.82513.5431.5911.50
GSP774.6074.5574.5574.5551.9742.83
TOTAL2626108.262682.822682.822679.821216.8715.58

Last Updated on 04/05/2021