ALAPPUZHA

SECTOR WISE

SECTORTOTAL PROJECTSPROJECT COST*AS ACCORDEDAS AMOUNT*TS ISSUEDTS AMOUNT*TENDEREDTENDERED AMOUNT*AWARDEDAWARDED AMOUNT*COMPLETEDEXPENDITUREEXPENDITURE %
WS10148.910150.7910150.7910150.798150.472111.5773.99
SEW510.0956.9323.0523.0500000.00
SWD14548.1514548.7514548.1714548.1714447.1811133.7469.21
UT2711.2279.05278.49278.49266.19123.0633.81
GSP84.3684.1684.1284.1284.0411.6038.43
TOTAL195222.70195219.68192214.62192214.62186207.88126149.9868.27
# WS – WATER SUPPLY, SEW- SEWERAGE & SEPTAGE MANAGEMENT, SWD- STORMWATER DRAINAGE, UT- URBAN TRANSPORT, GSP- GREEN SPACE & PARKS
*Amount in Crore

AGENCY WISE [KWA]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
WS1010150.7910150.7910150.798150.472111.5874.00
TOTAL1010150.7910150.7910150.798150.472111.5874.00

AGENCY WISE [ULB]

SECTORTOTAL PROJECTSAS ACCORDEDAS AMOUNTTS ACCORDEDTS AMOUNTTENDEREDTENDERED AMOUNTAWARDEDAWARDED AMOUNTCOMPLETEDEXPENDITUREEXPENDITURE%
SEW556.9323.0523.0500000
SWD14514548.7514548.1714548.1714447.1811133.7469.21
UT27279.05278.49278.49266.19123.0633.81
GSP884.1684.1284.1284.0411.6038.43
TOTAL18518568.8918263.8318263.8317857.4112438.4055.74

Last Updated on 06/06/2021