AMRUT – Accelerated Review  – as on January 2020

 

        1st November 2019 : The Additional Chief Secretary of LSG Department has initiated a series of Accelerated Review Meetings regarding the progress of implementation of AMRUT in Kerala.

 

       The Additional Chief Secretary, LSGD analysed the present status of the project implemented by KWA and ULB separately as per the data submitted by SMMU Team and directed the SMMU Experts to vigorously monitor on daily basis the four pending milestones ie., TS issuance, Tendering, Work awarding and Awarded but Not Started Projects. The pendency details as follows.

 

Kerala

Awarded But not Started Tendered But Not Awarded TS issued but not tendered AS issued but TS pending
Num Amount in Cr Num Amount in Cr Num Amount in Cr Num Amount in Cr
Water Supply – KWA 8 45.70 4 26.3 0 0 1 6
 Sewerage – KWA 3 10.09 24 105.17 0 0 0 0
Total KWA 11 55.79 28 131.47 0 0 1 6
WS – Non KWA 3 3.12 2 .53 0 0 0 0
SEW – Non KWA 3 2.31 14 257.67 0 0 2 1.1
Storm Water Drainage  13 5.21 1 8.41 0 0 0 0
Urban Transport 10 14.60 3 19.65 2 4.31 0 0
Green Spaces & Parks 0 0 2 0.68 0 0 0 0
Total Non – KWA 29 25.24 22 286.94 2 4.31 2 1.1
Grand Total 40 81.03 50 418.41 2 4.31 3 7.1

 

Progress in Pending Milestones 

Kerala

Awarded But not Started Tendered But not Awarded TS issued but not tendered AS issued but TS pending
Num Amount in Cr Num Amount in Cr Num Amount in Cr Num Amount in Cr
KWA projects 11 55.79 28 131.47 0 0 1 6
Non-KWA projects 29 25.24 22 286.94 2 4.31 2 1.1
Total Pendency 40 81.03 50 418.41 2 4.31 3 7.1