ALAPPUZHA
SECTOR WISE
SECTOR | TOTAL PROJECTS | PROJECT COST* | AS ACCORDED | AS AMOUNT* | TS ISSUED | TS AMOUNT* | TENDERED | TENDERED AMOUNT* | AWARDED | AWARDED AMOUNT* | COMPLETED | EXPENDITURE | EXPENDITURE % |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
WS | 9 | 150.78 | 9 | 150.76 | 9 | 150.76 | 9 | 150.76 | 9 | 150.74 | 8 | 139.23 | 92.35 |
SEW | 4 | 10.09 | 4 | 6.49 | 4 | 6.49 | 4 | 6.49 | 2 | 3.05 | 0 | 0.63 | 9.71 |
SWD | 151 | 48.17 | 151 | 48.17 | 151 | 48.17 | 151 | 48.17 | 149 | 46.17 | 141 | 42.41 | 88.04 |
UT | 29 | 9.29 | 29 | 9.29 | 29 | 9.29 | 29 | 9.29 | 27 | 7.88 | 25 | 4.95 | 53.28 |
GSP | 8 | 4.36 | 8 | 4.36 | 8 | 4.12 | 8 | 4.12 | 8 | 4.04 | 5 | 3.05 | 69.95 |
TOTAL | 201 | 222.69 | 201 | 219.07 | 201 | 218.83 | 201 | 218.83 | 195 | 211.88 | 179 | 190.27 | 86.85 |
*Amount in Crore